Skip to main content

Coming 2026

Updates

Public Engagement (Summer 2021)

100%

Initial Concept Plan (Summer 2021)

100%

Design

85%

Construction (February 2024 - Mid 2026)

10%

Final design is subject to change

Construction Updates

Progress Update
Exciting developments are underway as the construction team continues to advance on the foundation system of the New Aquatics Facility.

  • Foundation Work: Concrete piles are in place, and the building’s outline is now visible with the new grade beams and pile caps.
  • Excavation: A large hole at the south end marks the start of the basement and deep end of the competition lap pool.
  • Next Steps: After excavation we’ll install footings and drainage systems, then construct the slabs and walls to bring the building up to grade.

What’s Been Completed
The first phase of construction began in February 2024, with early works clearing the site and preparing it for the main phase of construction. This phase involved relocating the existing water main and installing new sanitary and storm sewers. It also included the selective demolition of external portions of the existing Bold Centre, such as the wooden pergola, landscaping, and traffic circle. The construction site has been expanded south toward 91 Ave. The site fence will remain in place until completion of the project in mid-2026.

Attention Bold Centre Visitors:

Please be advised that starting October 15, 2024, work will start on constructing a new secondary access to the Bold Centre through the food court due to the construction of the New Aquatics Facility.

After that work is complete (estimated to take about one week), the main (east) entrance of the Bold Centre will be closed.

Although there will always be access to the building through the east side, we encourage staff and patrons to utilize the west entrance on the opposite side of the building.

Thank you for your cooperation and understanding during this time as we work diligently to bring this exciting new facility to life!

Project Overview

Located at the Bold Centre, the New Aquatics Facility is a multi-feature project designed to meet the needs and priorities of our community. Informed by findings from the public engagement process, the facility will include dynamic elements like a lazy river, teaching and leisure pool, a six-lane competition pool, two waterslides (one large and one for tots), two hot tubs and a outdoor patio and hot tub among other exciting amenities. There will be something for everyone to enjoy throughout the winter and summer months at the Bold Centre.

The project takes a Progressive Design-Build approach and is slated for completion in 2026.

Community Impact

Quality of Life:

The New Aquatics Facility is all about enhancing the quality of life, health and wellness of our community. From fitness programs to leisure opportunities, the New Aquatics Facility at the Bold Centre will provide a safe, comfortable, and convenient place for families, youth, adults and seniors to meet, stay active, and engage with other community members.

Community Health & Wellness:

The New Aquatics Facility will provide residents with easy access to aquatic recreation, leisure and fitness opportunities that can positively impact overall health.

Strengthen our Community:

As an amenity that will attract new residents and visitors to the County, the Bold Centre New Aquatics Facility supports our growth and sustainability as a community and positions Lac La Biche as an athletic hub for sport tourism.

Final design is subject to change

Facility

Features

Key facility amenities include leisure pool with resort deck, beach entry, fun elements and teaching area; lazy river with engaging, play features; two waterslides (one large and one for tots); 25-metre, six lane competition lap pool with pool deck; diving board; family and adult-only hot tubs; outdoor patio and hot tub; steam room and sauna; and multipurpose space available for bookings.

Images

The images above indicate the general design intent only. Final design is subject to change in response to project requirements.

FAQs

HOW IS THIS FUNDED? 

Funding for the New Aquatics Facility includes a provincial grant of $9 million, a federal grant of $6 million and a County commitment of $29.9 million for an overall project budget of $44.9 million. 

WHY IS THE AQUATICS FACILITY A GOOD MOVE FOR THE COUNTY? 

The Bold Centre New Aquatics Facility will strengthen the community by providing new economic opportunities, enhancing quality of life, and creating new ways to promote health and wellness for all County residents. With the existing Portage Pool approaching the end of its life, aquatics operating costs will decrease with a new, modernized facility and provide more features and services tailored to the needs and priorities of the community. 

WHEN WILL THE AQUATICS FACILITY OPEN? 

The New Aquatics Facility is planned to open mid 2026. The County is working closely with the project team to review the project and schedule requirements and will keep the community informed as the project progresses. 

WHAT WILL THE AQUATICS FACILITY FEATURE? 

The approved project budget of $44.9 million includes the following key facility amenities: leisure pool with resort deck, beach entry, fun elements and teaching area; lazy river with engaging, play features; two waterslides (one large and one for tots); 25-metre, six lane competition lap pool with pool deck; diving board; family and adult-only hot tubs; Nordic spa and wellness area; steam room and sauna; and multipurpose space available for bookings.  

WHY IS THE NEW DESIGN DIFFERENT FROM THE CONCEPT WE SAW BEFORE? 

The concept plan for the New Aquatics Facility was developed based on ideas and input collected from the community in Spring 2021. The concept plan identified a general layout that captured the desired features identified by the community. This general idea has been further developed by the project team in response to a deeper understanding of the project requirements and technical details.   

WHAT DOES PROGRESSIVE DESIGN-BUILD MEAN? 

Progressive Design-Build refers to a project delivery model that promotes a collaborative approach between the County, design and construction partners who work together from the outset of a project to ‘progress’ to a final design and construction contract price. Key advantages include that it is faster than traditional delivery methods like Design-Bid-Build or Design-Build, and it offers better protection against the typical design, schedule and cost risks encountered on every project.   

WHERE IS IT GOING TO BE LOCATED? 

The New Aquatics Facility will be attached to the Bold Centre as generally identified in the concept plan, including shared parking and other amenities.  

WHAT TYPE OF PROGRAMMING CAN I EXPECT? 

Programming will be offered that reflects the needs and priorities of the community. The New Aquatics Facility will offer more programs than the Portage Pool, including the delivery of some new programs. 

WILL THERE BE DROP-IN LANE SWIMMING/FITNESS TIME? 

Yes, lane swimming will be available at the New Aquatics Facility. The plan is to create a schedule for fitness-focused time that meets these needs of the community. 

WHAT IS THE PLAN FOR THE CHANGE ROOMS? 

Change rooms have been carefully designed and sized according to community needs and facility requirements. A flexible, modular layout has been provided that offers both traditional gendered and universal design formats. 

WILL THE NEW FACILITY BE ABLE TO HOST REGIONAL SWIMMING COMPETITIONS? 

Yes, the New Aquatics Facility will be capable of hosting regional swimming competitions. Together with the many other recreational and competitive sporting features of the Bold Centre, it will help position the County as a regional hub for sporting events.  

WHAT WILL BE THE ADMISSION COST? 

Our primary goal is to ensure that everyone in the community can access the New Aquatics Facility. Accessibility and affordability will be top of mind as the County considers admission and program costs.  

WILL THE CONSTRUCTION AFFECT THE HOURS OF OPERATION FOR THE BOLD CENTRE? 

Construction of the New Aquatics Facility will be carefully managed to minimize disruptions to the ongoing operation of the Bold Centre, including Public Library and J.A. Williams High School. The team will communicate any required changes to parking or building access as early as possible to decrease the potential impacts on Bold Centre attendees, high school students, library visitors and all staff. We thank you in advance for your patience as we work to complete this incredible project as soon as possible. 

HOW DOES THE SIZE OF THE NEW AQUATICS FACILITY COMPARE TO THE EXISTING PORTAGE POOL? 

While the design is ongoing and subject to change, the New Aquatics Facility will bring the following larger sizes:

  • The new 25m lap pool is approximately 50% larger than the Portage Pool, and includes six swim lanes
  • The new leisure pool is approximately 120% larger than the Portage Pool, and includes beach entry, a teaching area and a lazy river
  • The three new hot pools are approximately 160% larger (combined) than the Portage Pool and include family, adult and outdoor options

WHERE CAN I GET MORE INFORMATION ABOUT THE PROJECT? WHERE SHOULD I DIRECT MY QUESTIONS? 

For ongoing project updates, please revisit BoldCentreAquatics.com. You can also direct questions by email to [email protected].

Partners

Contact

We expect you will have many questions as we move through this project, and we are committed to answering them the best we can. Our goal is to be transparent in our plans and provide the community with as much information as possible at every step. Please email [email protected] with additional questions.